> Does anyone have or has anyone found a more systematic
> method of creating a PERT chart?
> Any comments?

I remember him saying a number of times "use Microsoft Project"...:-)

However, both styles are telling you exactly the same information. All jobs
have a duration -  earliest/latest start/finish times only come into effect
when there is more than one path to the node. You then just find the
smallest/largest cumulative job duration.

A quick search for Pert gave this fairly straight forward site:

http://www.uwf.edu/~coehelp/studentaccounts/rnew/perthome.html